Name of Project: Construction of Jiaxing High Speed Rail Station
Engineering materials: reinforcement of plastic
Project Time: 2008
Jiaxing high-speed railway station is located in Jiaxing City, South Lake District, Yu Xinzhen, with a total area of 75,271 square meters, the main sub-station building and parking lot in two parts. Among them, the station building a total area of 55,904 square meters, by the station station, platform canopy, underground passageway, cross-line bridge and other components. The ground floor is designed for the ticket hall, ticket room, waiting room and staff office; on the floor of the second floor of the station is divided into three floors: the main floor is designed for the cold room, fire water tanks, living pressurized water pump room; Layer for the waiting room, infirmary, men and women bathroom, kitchen and so on. Waiting room is the highlight of the station, divided into ordinary waiting room, barrier waiting room, group waiting room, VIP rooms and other parts.
ANDME company, Andreas has a team of professional reinforcement products and execution teams. During the construction of the project, a lot of efforts have been made to reinforce the construction of the foundation. The new reinforcement products and reinforcement technology have been used extensively to make the building more stable. Steps.